World’s largest offshore wind farm begins construction in U.K.

The first of what will be 174 800-ton monopiles has been installed at the site 120 kilometers (75 miles) off the coast of Yorkshire, UK. They will support the 174 Siemens 7.0MW turbines.

The wind farm is being developed by Ørsted, (formerly DONG Energy), a power company based in Fredericia, Denmark. Ørsted is the largest energy company in Denmark. The company adopted its current name on 6 November 2017.

Expected to be operational in 2020, Hornsea Project One will produce enough power for over one million homes. The total combined 1.2 gigawatts of capacity will be about as much as the largest nuclear reactors.

‘The most powerful heavy-life jack up vessel.' The ship – Innovation – has a load capacity o...

‘The most powerful heavy-life jack up vessel.’ The ship – Innovation – has a load capacity of 8,000 tons and can install in waters up to a 65 meter depth.
Ørsted


According to Ørsted, the installation is being carried out by GeoSea’s installation vessel, Innovation. It will carry up to 4 monopiles at a time, each one is 65 meters (213 feet) long, weighs around 800 tons and has a diameter of 8.1 meters (27 feet)

Innovation is a self-elevating vessel which can extend four legs down to the ocean floor and jack itself up to act as a stationary offshore installation platform. The vessel has a capacity of 31,400 tons and can accommodate 100 people onboard.

Innovation will also be used to install some of the transition pieces in the project. Next month, Innovation will be joined by A2Sea’s vessel Sea Installer to continue with transition piece installation.

According to Ørsted, an 8MW turbine – the MH1 by Vestas – generates enough electricity in one revolution of the turbine blades to power a house for 29 hours. However, the Siemens SWT-7.0-54 turbine will generate 25 hours of electricity with a single rotation. The individual blades are 75 meters (246 feet) long and the total area covered when the blades spin is, 18,600m2 (4.6 acres).

The individual blades are 75 meters long and the total area covered when the blades spin is  18 600m...

The individual blades are 75 meters long and the total area covered when the blades spin is, 18,600m2 (4.6 acres).
Ørsted


In a press release, Duncan Clark, program director for the project, said, “After years of planning it is fantastic to see the initial stages of offshore construction begin. My thanks to the teams working day and night on this significant milestone.”

“Onshore, we are continuing to construct the East Coast Hub which will serve as an operations and maintenance base for our existing wind farms in the area and both Hornsea Project One, and Project Two which we took a final investment decision on last year. These wind farms will not only greatly contribute to the UK’s goal of decarbonizing our energy system, they are also bringing jobs and investment to Grimsby and the North East.”

SEA INSTALLER is designed to transport and install up to eight 4MW turbines or four 8.3MW turbines. ...

SEA INSTALLER is designed to transport and install up to eight 4MW turbines or four 8.3MW turbines. And, with a reinforced deck as long as a football pitch, she’s made to carry large, heavy loads.
A2SEA


Ørsted’s press release described the company as the biggest offshore wind farm developer in the world, with the UK as their largest market. They boast two operational wind farms off the nation’s east coast, Lincs and Westermost Rough. Another offshore wind farm, Race Bank, is slated to open later in 2018.

Avatar photo
Written By

We are deeply saddened to announce the passing of our dear friend Karen Graham, who served as Editor-at-Large at Digital Journal. She was 78 years old. Karen's view of what is happening in our world was colored by her love of history and how the past influences events taking place today. Her belief in humankind's part in the care of the planet and our environment has led her to focus on the need for action in dealing with climate change. It was said by Geoffrey C. Ward, "Journalism is merely history's first draft." Everyone who writes about what is happening today is indeed, writing a small part of our history.

You may also like:

Business

Chinese students at an e-commerce school rehearse selling hijabs and abayas into a smartphone - Copyright AFP Jade GAOJing Xuan TENGDonning hijabs and floor-length...

World

US President Joe Biden delivers remarks after signing legislation authorizing aid for Ukraine, Israel and Taiwan at the White House on April 24, 2024...

World

AfD leaders Alice Weidel and Tino Chrupalla face damaging allegations about an EU parliamentarian's aide accused of spying for China - Copyright AFP Odd...

Business

Meta's growth is due in particular to its sophisticated advertising tools and the success of "Reels" - Copyright AFP SEBASTIEN BOZONJulie JAMMOTFacebook-owner Meta on...