NASA chief acknowledges more trouble with SLS rocket

-

The US space agency NASA on Wednesday cast a shadow on the future of its new heavy-lift rocket, the SLS -- acknowledging development delays on a project that is already years behind.

The Space Launch System program is being run much as the Apollo and space shuttle mission were handled in the days of old.

READ MORE: NASA's Space Launch System may be replaced by commercial rockets

But Wednesday's announcement illustrates how quickly NASA has embraced a new era dominated by private space companies who are offering the option of low-cost transport on a mission-by-mission basis.

"SLS is struggling to meet its schedule" and won't be ready in time for a first unmanned mission around the Moon and back, dubbed EM-1, set for June 2020, NASA administrator Jim Bridenstine told lawmakers.

"Last week, it came to our attention that we're not going to be able to maintain the schedule," which is already three years behind, he told the Senate Commerce, Science and Transportation Committee.

Boeing has spent years developing the SLS, which would be the most powerful rocket ever built, with the goal of resuming manned space missions to the Moon. The project has already cost $12 billion.

A capsule for astronauts, Orion, is being built by Lockheed-Martin and Europe for the missions.

Wednesday marked the first time that NASA has clearly acknowledged the extent of the problems with the SLS.

That news did not surprise industry analysts, who have signaled problems with the development of the SLS for years.

Boeing is using more than 1,000 subcontractors in 43 US states to get the job done. That translates to thousands and thousands of jobs.

This file artist concept image from NASA shows the next generation of heavy-lift rocket  the Space L...
This file artist concept image from NASA shows the next generation of heavy-lift rocket, the Space Launch System -- which has once again been delayed
HO, NASA/AFP

Congress initially wanted a first flight in late 2016. NASA then pushed back the date little by little.

But Bridenstine then made the shocking announcement that he wants to entrust the EM-1 mission to existing private launch systems, instead of waiting for SLS to be ready.

"We have amazing capability that exists right now that we can use off the shelf in order to accomplish this objective," he said.

He did not specify which private company he had in mind, but SpaceX -- founded by billionaire Elon Musk -- would be a natural candidate with its Falcon Heavy rocket.

The Delta IV Heavy of United Launch Alliance -- a joint venture of Lockheed and Boeing -- also would be a capable alternative.

- Congress will have to decide -

NASA Administrator Jim Bridenstine made the surprise announcements about the SLS program before the ...
NASA Administrator Jim Bridenstine made the surprise announcements about the SLS program before the Senate Commerce, Science and Transportation Committee
CHIP SOMODEVILLA, GETTY IMAGES NORTH AMERICA/AFP

The new plan would consist of launching the Orion capsule, and then following it up with the launch of an upper stage for propulsion.

The two elements would then dock in orbit for the voyage around the Moon.

No rocket in existence today is capable of lifting both elements together, because of their weight, which is why NASA had said it needed the more powerful SLS.

"I want to be clear, we do not have right now an ability to dock the Orion crew capsule with anything in orbit. So between now and June of 2020, we would have to make that a reality," Bridenstine said.

One skeptical senator reminded him: "This is 2019...."

Bridenstine replied: "NASA has a history of not meeting launch dates, and I'm trying to change that."

The administration of President Donald Trump has made it clear that it is unhappy with all the delays.

A 1:50 scale model of NASA's Space Launch System (SLS) is displayed at the agency's booth ...
A 1:50 scale model of NASA's Space Launch System (SLS) is displayed at the agency's booth during the Consumer Electronics Show in Las Vegas on January 11, 2018
Ethan Miller, GETTY IMAGES NORTH AMERICA/AFP/File

In its budget proposal unveiled on Monday, the government wants to let the private sector launch the components of the mini-space station, dubbed the Gateway, that NASA wants to put in orbit around the Moon in the 2020s.

It also decided that private companies would launch a probe towards Jupiter's moon Europa.

Both of those missions were initially expected to be carried out using the SLS.

In the end, Congress will have to decide whether to pass the space budget as is or request changes that would preserve the SLS program's place in upcoming missions.

Producing the SLS in 43 states means 86 senators have something to lose if the SLS program goes south, leading some snarky commentators to label it the "Senate Launch System."

The budget for 2020 should be adopted in the coming months.

The US space agency NASA on Wednesday cast a shadow on the future of its new heavy-lift rocket, the SLS — acknowledging development delays on a project that is already years behind.

The Space Launch System program is being run much as the Apollo and space shuttle mission were handled in the days of old.

READ MORE: NASA’s Space Launch System may be replaced by commercial rockets

But Wednesday’s announcement illustrates how quickly NASA has embraced a new era dominated by private space companies who are offering the option of low-cost transport on a mission-by-mission basis.

“SLS is struggling to meet its schedule” and won’t be ready in time for a first unmanned mission around the Moon and back, dubbed EM-1, set for June 2020, NASA administrator Jim Bridenstine told lawmakers.

“Last week, it came to our attention that we’re not going to be able to maintain the schedule,” which is already three years behind, he told the Senate Commerce, Science and Transportation Committee.

Boeing has spent years developing the SLS, which would be the most powerful rocket ever built, with the goal of resuming manned space missions to the Moon. The project has already cost $12 billion.

A capsule for astronauts, Orion, is being built by Lockheed-Martin and Europe for the missions.

Wednesday marked the first time that NASA has clearly acknowledged the extent of the problems with the SLS.

That news did not surprise industry analysts, who have signaled problems with the development of the SLS for years.

Boeing is using more than 1,000 subcontractors in 43 US states to get the job done. That translates to thousands and thousands of jobs.

This file artist concept image from NASA shows the next generation of heavy-lift rocket  the Space L...

This file artist concept image from NASA shows the next generation of heavy-lift rocket, the Space Launch System — which has once again been delayed
HO, NASA/AFP

Congress initially wanted a first flight in late 2016. NASA then pushed back the date little by little.

But Bridenstine then made the shocking announcement that he wants to entrust the EM-1 mission to existing private launch systems, instead of waiting for SLS to be ready.

“We have amazing capability that exists right now that we can use off the shelf in order to accomplish this objective,” he said.

He did not specify which private company he had in mind, but SpaceX — founded by billionaire Elon Musk — would be a natural candidate with its Falcon Heavy rocket.

The Delta IV Heavy of United Launch Alliance — a joint venture of Lockheed and Boeing — also would be a capable alternative.

– Congress will have to decide –

NASA Administrator Jim Bridenstine made the surprise announcements about the SLS program before the ...

NASA Administrator Jim Bridenstine made the surprise announcements about the SLS program before the Senate Commerce, Science and Transportation Committee
CHIP SOMODEVILLA, GETTY IMAGES NORTH AMERICA/AFP

The new plan would consist of launching the Orion capsule, and then following it up with the launch of an upper stage for propulsion.

The two elements would then dock in orbit for the voyage around the Moon.

No rocket in existence today is capable of lifting both elements together, because of their weight, which is why NASA had said it needed the more powerful SLS.

“I want to be clear, we do not have right now an ability to dock the Orion crew capsule with anything in orbit. So between now and June of 2020, we would have to make that a reality,” Bridenstine said.

One skeptical senator reminded him: “This is 2019….”

Bridenstine replied: “NASA has a history of not meeting launch dates, and I’m trying to change that.”

The administration of President Donald Trump has made it clear that it is unhappy with all the delays.

A 1:50 scale model of NASA's Space Launch System (SLS) is displayed at the agency's booth ...

A 1:50 scale model of NASA's Space Launch System (SLS) is displayed at the agency's booth during the Consumer Electronics Show in Las Vegas on January 11, 2018
Ethan Miller, GETTY IMAGES NORTH AMERICA/AFP/File

In its budget proposal unveiled on Monday, the government wants to let the private sector launch the components of the mini-space station, dubbed the Gateway, that NASA wants to put in orbit around the Moon in the 2020s.

It also decided that private companies would launch a probe towards Jupiter’s moon Europa.

Both of those missions were initially expected to be carried out using the SLS.

In the end, Congress will have to decide whether to pass the space budget as is or request changes that would preserve the SLS program’s place in upcoming missions.

Producing the SLS in 43 states means 86 senators have something to lose if the SLS program goes south, leading some snarky commentators to label it the “Senate Launch System.”

The budget for 2020 should be adopted in the coming months.

AFP
Written By

With 2,400 staff representing 100 different nationalities, AFP covers the world as a leading global news agency. AFP provides fast, comprehensive and verified coverage of the issues affecting our daily lives.

You may also like:

World

US President Joe Biden delivers remarks after signing legislation authorizing aid for Ukraine, Israel and Taiwan at the White House on April 24, 2024...

Business

Meta's growth is due in particular to its sophisticated advertising tools and the success of "Reels" - Copyright AFP SEBASTIEN BOZONJulie JAMMOTFacebook-owner Meta on...

Business

The job losses come on the back of a huge debt restructuring deal led by Czech billionaire Daniel Kretinsky - Copyright AFP Antonin UTZFrench...

Tech & Science

TikTok on Wednesday announced the suspension of a feature in its spinoff TikTok Lite app in France and Spain.